SONOQUI WASH CHANNEL

ANTICIPATED TO BEGIN: NOVEMBER/DECEMBER 2017       

ANTICIPATED COMPLETION: SPRING 2018

PROJECT DESCRIPTION

The Sonoqui Wash channel will extend east from Ellsworth Road to the Crismon Road alignment.

STATUS UPDATE

The cultural resource evaluation and archaeological data recovery work has been completed for the project.  This was necessary since the channel passes through the Pozos de Sonoqui archaeological site.

During construction, an archaeologist will be monitoring the wash excavation for the west half of the project. The Town of Queen Creek is in the process of bidding the project and work is anticipated to begin in November or December 2017.  

UPCOMING MEETINGS

No meetings currently scheduled.

For project information, please contact our project hotline at 480.898.4090.

QC-Construction-Logo-Horiz-FINALFor more information about our Capital Improvement Program, contact Troy White, Public Works Director at 480-358-3746 or troy.white@queencreek.org.

To submit questions or comments about this project visit our Capital Improvement Project Feedback Page.


 